Prepare for the AACE International Certified Cost Professional (CCP) Exam exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.
QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the AACE International CCP exam and achieve success.
Which of the following are used for profitability analysis in a construction company?
In a construction company, profitability analysis typically involves calculating the Return on Investment (ROI) and Rate of Return (ROR). ROI measures the profitability of an investment by comparing the gain from the investment to its cost, while ROR calculates the percentage return on each dollar invested. These metrics are critical in determining the financial performance and efficiency of investments in the construction industry.
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)
To calculate the total percentage increase in steel prices over three years, we compound the inflation rates for each year:
Year 1: 2.5%
Year 2: 2.5%
Year 3: 3.0%
The formula to calculate the total percentage increase is:
TotalIncrease=(1+RateYear1)(1+RateYear2)(1+RateYear3)1\text{Total Increase} = (1 + \text{Rate Year 1}) \times (1 + \text{Rate Year 2}) \times (1 + \text{Rate Year 3}) - 1TotalIncrease=(1+RateYear1)(1+RateYear2)(1+RateYear3)1 TotalIncrease=(1+0.025)(1+0.025)(1+0.03)1\text{Total Increase} = (1 + 0.025) \times (1 + 0.025) \times (1 + 0.03) - 1TotalIncrease=(1+0.025)(1+0.025)(1+0.03)1 \text{Total Increase} = 1.025 \times 1.025 \times 1.03 - 1 \approx 1.082 - 1 = 0.082 \text{ or 8.2%}
So, the correct answer is B. 8.2%.
A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:
The longest path depends upon relationships driving the timing of activity starts, therefore the following scheduling features should not be used in calculating file longest path.
In project management, the Critical Path Method (CPM) is used to determine the longest path of planned activities to the end of the project. This path determines the shortest possible duration to complete the project. The longest path in CPM is defined by the sequence of activities that have zero float (slack) and must be completed on time to avoid delaying the project.
Key Points:
Milestone Activities:
Milestones are significant points or events in the project timeline, representing the completion of a major phase or segment of the project.
They do not consume time or resources themselves and do not have a duration, so they do not contribute to the calculation of the longest path. Instead, they are used as reference points to mark significant events or deadlines within the project.
Activities with Lag:
Lags are intentional delays between activities, and while they can influence the start and finish of subsequent tasks, they do contribute to the determination of the longest path if those activities are on the critical path.
Activities with Short Durations:
Activities with short durations may still be on the critical path, as they can be linked sequentially to other critical tasks, thereby affecting the overall project duration.
Constraints, Resource Leveling, and Interruptible Activities:
These factors can affect the timing of activities and may extend or compress the critical path depending on the specific resource and scheduling constraints.
Conclusion: The correct answer is A. Milestone activities because these activities, being non-duration tasks, do not contribute to the calculation of the longest path. The focus should be on the tasks that consume time and resources and are interlinked in a way that affects the project's completion date.
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the "book value (BV) of the asset at the end of 5 years?
Given Scenario:
You need to calculate the book value (BV) of the asset at the end of 5 years using straight-line depreciation.
The straight-line depreciation formula is: AnnualDepreciation=CostSalvageValueUsefulLife\text{Annual Depreciation} = \frac{\text{Cost} - \text{Salvage Value}}{\text{Useful Life}}AnnualDepreciation=UsefulLifeCostSalvageValue
Initial Cost: $80,000
Salvage Value: $0 (since there's no salvage value)
Useful Life: 25 years
Annual Depreciation: 80,00025=3,200\frac{80,000}{25} = 3,2002580,000=3,200 per year
Book Value after 5 years:
BookValue=Cost(5AnnualDepreciation)=80,000(53,200)=80,00016,000=64,000\text{Book Value} = \text{Cost} - (5 \times \text{Annual Depreciation}) = 80,000 - (5 \times 3,200) = 80,000 - 16,000 = 64,000BookValue=Cost(5AnnualDepreciation)=80,000(53,200)=80,00016,000=64,000
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current schedule performance index (SPI)?
The Schedule Performance Index (SPI) is calculated using the formula:
SPI=EarnedValue(EV)PlannedValue(PV)\text{SPI} = \frac{\text{Earned Value (EV)}}{\text{Planned Value (PV)}}SPI=PlannedValue(PV)EarnedValue(EV)
Given:
Total Budgeted Hours = 12,000 hours
Planned Completion = 75%
Percent Complete = 66%
EV=12,0000.66=7,920hours\text{EV} = 12,000 \times 0.66 = 7,920 \text{ hours}EV=12,0000.66=7,920hours PV=12,0000.75=9,000hours\text{PV} = 12,000 \times 0.75 = 9,000 \text{ hours}PV=12,0000.75=9,000hours SPI=7,9209,0000.88\text{SPI} = \frac{7,920}{9,000} \approx 0.88SPI=9,0007,9200.88
So, the correct answer is B. 0.88.
Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits
Get All 189 Questions & Answers