Limited-Time Offer: Enjoy 60% Savings! - Ends In 0d 00h 00m 00s Coupon code: 60OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent APICS CPIM-Part-2 Exam Questions & Answers


Prepare for the APICS Certified in Planning and Inventory Management (Part 2) exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the APICS CPIM-Part-2 exam and achieve success.

The questions for CPIM-Part-2 were last updated on Dec 21, 2024.
  • Viewing page 1 out of 30 pages.
  • Viewing questions 1-5 out of 151 questions
Get All 151 Questions & Answers
Question No. 1

Which of the following trade-offs should be evaluated when determining where to place inventory in a multi-echelon supply chain network?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

A factory work center has the following work orders. What is the load on this work center?

Show Answer Hide Answer
Correct Answer: D

The load on a work center is the total time required to complete all the work orders assigned to that work center. The load can be calculated by multiplying the quantity and the run time of each work order, and then adding them up. The formula is:

Load = (Q1 x R1) + (Q2 x R2) + ... + (Qn x Rn)

Where Q is the quantity and R is the run time of each work order.

Using the data from the table, we can plug in the values and get:

Load = (10 x 8) + (15 x 9) + (12 x 7.5) + (20 x 10) + (8 x 6.5) = 80 + 135 + 90 + 200 + 52 = 557

Therefore, the load on this work center is 557 hours.


Question No. 3

The cost accountant has discovered a consistent overage in actual run time for one operation. This information should be sent first to the:

Show Answer Hide Answer
Correct Answer: D

The information about the consistent overage in actual run time for one operation should be sent first to the engineering manager to evaluate the run time for the routing. A routing is a document that specifies the sequence of operations and work centers required to produce a product or feature. A run time is the amount of time needed to perform an operation or a task at a work center. An overage in actual run time means that the actual time spent on an operation or a task is more than the planned or standard time. This can result in lower efficiency, productivity, or quality, as well as higher costs, waste, or delays.

The engineering manager is responsible for designing and maintaining the routing and the run time for each operation or task. The engineering manager can evaluate the run time for the routing by comparing the actual and planned times, identifying the causes of the overage, and taking corrective actions. For example, the engineering manager may:

Review the accuracy and validity of the planned or standard time, and update it if necessary.

Analyze the performance and capability of the machines, equipment, or labor involved in the operation or task, and improve them if needed.

Investigate the presence of any errors, defects, rework, or variability in the operation or task, and eliminate them if possible.

Implement lean production techniques, such as value stream mapping, waste reduction, or continuous improvement, to optimize the operation or task.

The other options are not appropriate for sending the information about the consistent overage in actual run time for one operation first. The product manager is not responsible for designing or maintaining the routing or the run time for each operation or task. The product manager is responsible for managing and marketing the product or feature, such as defining its specifications, features, price, or promotion. Increasing the selling price of the product is not a solution for addressing the overage in actual run time, as it may reduce customer demand or satisfaction, as well as increase competition. The quality manager is not responsible for designing or maintaining the routing or the run time for each operation or task. The quality manager is responsible for ensuring and improving the quality of the product or feature, such as setting quality standards, implementing quality control methods, or conducting quality audits. Adding a new quality measurement to the operation is not a solution for addressing the overage in actual run time, as it may increase complexity or cost without improving efficiency or productivity. The production supervisor is not responsible for designing or maintaining the routing or the run time for each operation or task. The production supervisor is responsible for overseeing and coordinating the production activities at a work center, such as scheduling operations, assigning resources, monitoring performance, or resolving issues. Reviewing and explaining the overage in actual run time is not a solution for addressing it, as it does not identify or eliminate its causes.


Question No. 4

A machine is suddenly having excessive downtime. Which of the following tools would be used in a root cause corrective action process to determine the problem?

Show Answer Hide Answer
Correct Answer: D

A3 method is a tool that can be used in a root cause corrective action process to determine the problem of a machine that is suddenly having excessive downtime.A3 method is a structured problem-solving approach that follows the Plan-Do-Check-Act (PDCA) cycle and uses a single sheet of paper (A3 size) to document the problem, analysis, countermeasures, and results1.A3 method can help identify the root cause of a problem by using tools such as the 5 Whys or the fishbone diagram, and then develop and implement effective corrective actions to prevent recurrence2.A3 method can also help communicate the problem and the solution to stakeholders, as well as monitor and evaluate the outcomes3.

The steps of the A3 method are4:

Step 1: Define the problem and its impact. Describe the current situation, the gap between the actual and the desired state, and the scope and magnitude of the problem.

Step 2: Identify the root cause of the problem. Use tools such as the 5 Whys or the fishbone diagram to analyze the factors that contribute to the problem and drill down to its root cause.

Step 3: Propose countermeasures to address the root cause. Generate possible solutions that can eliminate or reduce the root cause, and evaluate their feasibility, effectiveness, and costs.

Step 4: Implement countermeasures. Select the best solution and plan how to execute it. Define the roles, responsibilities, resources, timeline, and expected outcomes of the implementation.

Step 5: Check results and process. Measure and compare the results before and after the implementation, and verify if the problem has been solved or improved. Also check if the process has been followed correctly and document any deviations or issues.

Step 6: Standardize successful processes or identify unresolved issues. If the results are satisfactory, standardize the new process and ensure that it is sustained. If not, identify the remaining or new issues and repeat the A3 method.

Therefore, A3 method is a tool that can be used in a root cause corrective action process to determine the problem of a machine that is suddenly having excessive downtime.


Question No. 5

The most relevant measure of customer service performance is:

Show Answer Hide Answer
Correct Answer: A

Customer service performance is the degree to which a product or service meets or exceeds customer expectations. The most relevant measure of customer service performance is how the customer perceives the service compared to what they expected. This measure reflects the customer's satisfaction and loyalty, which are key factors for business success. Other measures, such as service promised versus measured, customer complaints, or positive feedback, are more related to the supplier's perspective and may not capture the customer's true perception of service quality.Reference: CPIM Part 2 Exam Content Manual, Domain 3: Plan and Manage Demand, Section A: Demand Management, Subsection 4: Customer Service Management, Page 11.


Unlock All Questions for APICS CPIM-Part-2 Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 151 Questions & Answers