Limited-Time Offer: Enjoy 60% Savings! - Ends In 0d 00h 00m 00s Coupon code: 60OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent Certinia PSA-Sysadmin Exam Questions & Answers


Prepare for the Certinia PSA System Administrator 2023 exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the Certinia PSA-Sysadmin exam and achieve success.

The questions for PSA-Sysadmin were last updated on Dec 21, 2024.
  • Viewing page 1 out of 12 pages.
  • Viewing questions 1-5 out of 60 questions
Get All 60 Questions & Answers
Question No. 1

Managers want to be able to edit expenses once they are marked as approved, "Include in Financials" is selected, but before the Billing Events are created. Which of the following options do you choose under the Permission Control record?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

A user is having an issue where the Utilization report has inflated hours. The billable hours, calendar hours, and credited hours are double their actual values.

Which of the following is a possible cause of this issue?

Show Answer Hide Answer
Correct Answer: C

Question No. 3

You are in the process of setting up your organization's Resources and learn that Resources in France will be working a 35-hour work week.

What will you need to do to set them up with the proper work calendar?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

Currently Project Managers and Resource Managers are using Gantt. You do not want your Project Managers creating assignment, resource requests or milestones from the Gantt. Which of the following custom settings should you configure to hide these buttons?

Show Answer Hide Answer
Correct Answer: B

Question No. 5

Your current setup of utilization automatically subtracts PSA Holidays from the total number of hours defined in a resource's "Work Calendar." How can utilization be configured so Holidays are not automatically subtracted?

Show Answer Hide Answer
Correct Answer: C