Prepare for the IBM Maximo Manage v8.0 Implementation exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the IBM C1000-132 exam and achieve success.

The questions for C1000-132 were last updated on Nov 20, 2024.
  • Viewing page 1 out of 13 pages.
  • Viewing questions 1-5 out of 64 questions
Get All 64 Questions & Answers
Question No. 1

In which two places can Service Request Categories be created for use in the Service Request Work Center?

Show Answer Hide Answer
Correct Answer: B, E

In IBM Maximo Manage, Service Request Categories can be created for use in the Service Request Work Center in two places - the Administration Work Center and the Service Catalog Application.


Question No. 2

In the Work Order Tracking application, a Work Order is generated from a Preventive Maintenance (PM) record. How is the target finish date calculated?

Show Answer Hide Answer
Correct Answer: C

In the Work Order Tracking application, when a Work Order is generated from a Preventive Maintenance (PM) record, the target finish date is calculated as the Work Order target start date + the Job Plan duration.


Question No. 3

When working with Purchase Requests, which statement is correct?

Show Answer Hide Answer
Correct Answer: B

When working with Purchase Requests in IBM Maximo Manage, one Purchase Request can contain both Item and Material type lines.


Question No. 5

When using flow control on a Work Order, how ca from the Parent to Child Work Orders?

user ensure that Work Order status changes are inherited

Show Answer Hide Answer
Correct Answer: B

When using flow control on a Work Order in IBM Maximo Manage, to ensure that Work Order status changes are inherited from the Parent to Child Work Orders, you should go to the Organization application and check the Inherit Status Changes flag in Work Order Options -> Flow Control Options.