Limited-Time Offer: Enjoy 50% Savings! - Ends In 0d 00h 00m 00s Coupon code: 50OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent iSQI CTFL-AT Exam Dumps

 

Prepare for the iSQI ISTQB Certified Tester - Agile Tester exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the iSQI CTFL-AT exam and achieve success.

The questions for CTFL-AT were last updated on Mar 31, 2025.
  • Viewing page 1 out of 8 pages.
  • Viewing questions 1-5 out of 40 questions
Get All 40 Questions & Answers
Question No. 1

Which agile development approach incorporates the following practices:

* a project is divided into iterations called sprints

* each sprint results in a potentially releasable/shippable product?

Show Answer Hide Answer
Correct Answer: D

Question No. 2

Which of the following statements about a test charter are CORRECT?

1) It is used mainly in exploratory tests.

2) It is used to monitor a test process.

3) It may make reference to user stories.

4) It contains notes taken during a test session.

5) It is used to outline the company test policy.

Show Answer Hide Answer
Correct Answer: C

Question No. 3

Which of the following statements about the Planning poker test estimate technique are CORRECT?

1) Planning poker is a consensus based technique using a deck of cards.

2) A low test estimate usually means the story should be broken down into multiple smaller stories.

3) A high test estimate usually means the story should be broken down into multiple smaller stories.

4) One poker round is played and then consensus has to be reached.

5) The risk level of each backlog item should be decided before the poker session.

Show Answer Hide Answer
Correct Answer: A

Question No. 4

You are developing the code that controls an industrial Espresso machine which will be operated by waiting staff in restaurants.

The machine is rather complicated and has lots of switches and buttons, so in the next iteration instructions will be provided to the operator on a small LCD screen.

A User Story for the Operator-Instructions module is as follows:

"As an operator of the Espresso machine, I would like to know how to steam milk, so I can add steamed milk to the coffee."

The following is a list of risks identified for this story, with assigned probability and impact.

Show Answer Hide Answer
Correct Answer: B

Question No. 5

Which of the following statements about Agile retrospectives is CORRECT?

Show Answer Hide Answer
Correct Answer: B