QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the Pegasystems PEGACPBA88V1 exam and achieve success.
Which project nears the end of the Prepare phase, you prepare the project plan for review with your development team, two elements does the project plan include? (Choose Two)
As a project nears the end of the Prepare phase, the project plan should include:
B . Epics and user stories:
These are essential for defining the work to be done in future sprints. They provide detailed descriptions of the functionality and requirements that need to be developed and tested.
C . RAID log (Risks, Actions, Issues, and Decisions):
This log is critical for tracking potential risks, ongoing actions, issues that need resolution, and decisions made during the project. It helps in managing and mitigating risks and ensures that the project stays on track.
Pega Academy: Project Planning and Management
Pega Documentation: Prepare Phase Activities and Deliverables
The development, your team creates a spreadsheet with work items to populate the backlog.
...you populate the backlog directly from the spreadsheet?
Import stories: When populating the backlog directly from a spreadsheet, the correct approach is to import the stories. Pega allows for importing user stories from spreadsheets to efficiently populate the backlog.
In the Travel booking case type, if a passenger indicates that they are traveling with a service animal, they must document the type, size, and age of the animal, ..do you configure the case life cycle to meet this requirement?
In Pega, conditional processes can be added to a case life cycle to handle specific scenarios, such as when a passenger is traveling with a service animal. By adding an Identify service animal process and applying a condition to determine when this process should run, you can ensure that the required information about the service animal is collected only when needed. This approach keeps the main case flow streamlined while handling special requirements as necessary.
The business process for an automobile insurance claim consists of the following phases:
* Submission: The customer contacts a customer service representative (CSR) to file the claim.
* Review: An adjuster reviews the claim, assesses the damages to each vehicle, and provides an estimate of the cost of repairs.
* Repair: A third party performs the repairs on each vehicle, communicating with the adjuster and customer as necessary.
* Verification: After each vehicle repair, the adjuster closes the claim.
According to Pega best practices, which phase can you implement as a child case?
Submission: This phase involves the initial contact and filing of the claim, which typically doesn't need to be a separate case as it's an initial action.
Review: This phase involves an adjuster reviewing the claim and assessing damages, which can be handled within the primary case.
Repair: The repair phase involves interaction with third-party vendors and ongoing communication, making it suitable to be implemented as a child case to track each repair separately.
Verification: This phase is a closing action performed after repairs, which doesn't typically require a separate case.
...a Pega Business Architect, your project is approaching the end of the Prepare phase.
Identify three aspects of the project plan that must be taken into consideration to successfully deliver an application that achieves the client's desired business outcomes loose Three)
Initiate planning of the next Minimum Lovable Product (MLP): Planning for the next MLP should begin towards the end of the current phase to maintain momentum and ensure continuous delivery. This involves defining the scope, requirements, and timeline for the next set of features.
Confirm the Sprint plan is achievable for delivering this Minimum Lovable Product (MLP): It is essential to ensure that the Sprint plan is realistic and achievable. This involves verifying that the team can complete the required work within the allotted time frame and that dependencies and resources are properly managed.