Question No. 1

Scenario

An internet banking organization plans to expand operations outside of its current market. Whilst the exact details have yet to be established, it is clear that the IT organization must expand its service offerings within the current portfolio in order to support this growth. It is equally apparent that external customer needs for banking will vary from market to market and that consequently this will require development of completely new service offerings.

You are the head of service within the IT organization. You helped the organization adopt the ITIL framework some years ago and now have most processes in place. Service owners are allocated for the main IT services. Mature service portfolio, service catalogue and service level management processes are in place.

The expansion requires ownership of a business relationship management process and you are considering the role profile for this post.

Refer to the Scenario.

Which one of the following options provides the BEST overview of the business relationship manager's (BRM) responsibilities which will be key to support the expansion?

Show Answer Hide Answer
Correct Answer: B

Question No. 2

Scenario

A clothing manufacturer has made a decision to supplement factory-based retail outlets by opening a series of stores at out-of-town shopping malls.

The internal IT organization provides support to many mission-critical business systems for both the manufacturing and retail operations. It must increase its portfolio of services and service options to meet the planned new expansion. Typically, the business is subject to seasonal patterns of demand, which recently have begun to exceed the capability of some of the IT services. This has led to periods of poor performance of some of the critical systems and therefore to degraded service quality. In periods of minimal demand, there is a surplus of capacity and performance is optimal.

There is concern that the additional business demand from the new stores will exacerbate these service performance issues.

The board of directors, made up of representatives from each business unit, has asked for a review of the business supply and demand issues currently being faced by the IT organization. Many service management processes have been implemented including service portfolio management and capacity management. However, IT does not have a demand management process.

Additionally, performance levels on many of the supporting services have remained unchanged for the past 3 years, even though some may now be less relevant to the overall performance of the critical services.

Refer to the Scenario.

The review of the supply and demand issues concluded that the implementation of a demand management process could help the IT organization address the issues. Which one of the following options provides the BEST solution to both the problems currently being faced and those related to the proposed expansion?

Show Answer Hide Answer
Correct Answer: A

Question No. 3

Scenario

A financial services organization has undergone a period of rapid expansion. From its operating base it has expanded to serve customers in over 25 countries spread around the globe. There are plans to enter more markets in the next 12 months.

The key stakeholders involved in the global expansion project have briefed the chief information officer (CIO) on the plans. They have identified IT service performance as one of the major threats to the plan. The CIO has been under pressure from the board due to poor IT service performance in the previous six months. The chief concern has been significant performance variations in network connectivity and communications.

The organization currently has three contracts with different local external suppliers in operating markets supporting three IT network hubs. Whilst the suppliers are all happy to follow local internal IT processes, getting the three to work together on incidents or changes has proved increasingly difficult.

A number of outages have resulted in a blame culture where even the local internal IT departments have been sympathetic to their service providers, resulting in strained relationships between these internal departments at an operational level.

Other issues encountered at one or more locations have included:

* Long-term service improvements have been sacrificed in favour of short-term fixes that avoid the payment of contract penalties by the suppliers

* Changes in ownership of the customer relationship by the suppliers

The CIO believes that a lack of communication between suppliers has been the key cause of failures.

All three supplier contracts are due for renewal in the next 12 months. After consultation, a decision to re-tender for network services has been taken by IT, and approved by the CIO and the board of directors.

Refer to the Scenario.

When considering suppliers, which one of the following options would BEST ensure that network issues are addressed in order to meet the needs of the financial services organization?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

Scenario

A flower delivery company introduced ITIL-based service management processes 12 months ago.

One major benefit of the associated service improvement initiatives was that the service availability of the business critical on-line flower ordering IT service increased from 97% to 98.9% over the last quarter. This exceeds the service availability target of 98.5%. Last month, reports were circulated showing the availability improvement.

The service level manager is chairing a service review meeting to review the progress and report upon this achievement. The customer managers acknowledge the improvement but despite the reports of improved service availability, a major service outage occurred during the busiest week of the year when over 25% of the annual business revenue is normally earned. Although IT dealt with the outage satisfactorily, the loss of revenue and credibility in this mission critical, high-visibility trading period are serious concerns. The customer managers are concerned that the reporting does not seem to reflect this or their actual perception of the service.

Agreement is reached at the meeting to address two primary concerns:

1. Service availability targets for the mission critical periods are to be revised.

2. Amended and more representative business reports are to be produced.

Refer to the Scenario.

Which one of the following options will BEST ensure that the primary concerns related to the revision and reporting of targets are addressed?

Show Answer Hide Answer
Correct Answer: C

Question No. 5

Scenario

A large, privately owned company has an internal IT organization that runs most of its IT operations from the head office. There has been a history of confusion about what is required from the services and what has actually been achieved, particularly from a warranty perspective. This has resulted in a strained relationship between the business units and the IT organization.

Some service-based agreements exist between IT and the customers, where all levels of response to incidents were set to the same targets. Availability targets have not been reviewed for at least two years. There have been a number of complaints by key customers claiming that the IT staff have been resolving incidents and implementing change requests based on operational ease rather than business priority. This is despite operationally robust processes being in place for incident, change and problem management.

A plan has been put in place to improve the level of the IT service delivered to the organization.

Retirement of the post-holder meant that the first action was to appoint a new IT director. The opportunity was taken to select a candidate from an external organization, who was committed to the ITIL framework. The new IT director believes that good IT service management practices are essential.

The IT director plans to implement many of the service management processes and has already overseen the creation of a basic service catalogue. The IT director is sure that many of the current issues can be rectified through the implementation of service level management (SLM) and has therefore directed that service level agreements (SLA) be introduced for the services provided before moving onto other areas. You have been asked to lead the project to establish SLAs for the IT services.

Refer to the Scenario.

Which one of the following sequence of activities would be the BEST approach to establishing service levels agreements (SLA) in the organization?

Show Answer Hide Answer
Correct Answer: A