Handsome Savings - Limited Time Offer 30% OFF - Ends In 0d 0h 0m 0s Coupon code: 50OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

PMI PMI-RMP Exam Actual Questions

The questions for PMI-RMP were last updated on Sep 30, 2024.
  • Viewing page 1 out of 55 pages.
  • Viewing questions 1-5 out of 273 questions
Unlock Access to All 273 Questions & Answers
Question No. 1

You are the project manager for the NHH project. You are working with your project team to examine the project from four different defined perspectives to increase the breadth of identified risks by including internally generated risks. What risk identification approach are you using in this example?

Show Answer Hide Answer
Correct Answer: B

Question No. 2

Ben works as a project manager for the MJH Project. In this project, Ben is preparing to identify stakeholders so he can communicate project requirements, status, and risks. Ben has elected to use a salience model as part of his stakeholder identification process. Which of the following activities best describes a salience model?

Show Answer Hide Answer
Correct Answer: D

Question No. 3

Gary is the project manager for his project. He and the project team have completed the qualitative risk analysis process and are about to enter the quantitative risk analysis process when Mary, the project sponsor, wants to know what quantitative risk analysis will review. Which of the following statements best defines what quantitative risk analysis will review?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

____ analysis is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen.

Show Answer Hide Answer
Correct Answer: B

Question No. 5

Todd is the project manager of the EST project for his company. His organization has established certain rules in the enterprise environmental factors which affect the approach that Todd takes in managing his project. One of the rules requires Todd to consider the risk attitude of the stakeholders participating in risk analysis. Why must risk attitude be considered as a part of risk analysis?

Show Answer Hide Answer
Correct Answer: A

Product Image

Unlock All Questions for PMI PMI-RMP Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 273 Questions & Answers