Limited-Time Offer: Enjoy 60% Savings! - Ends In 0d 00h 00m 00s Coupon code: 60OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent PMI-RMP Exam Questions & Answers


Prepare for the PMI Risk Management Professional exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the PMI-RMP exam and achieve success.

The questions for PMI-RMP were last updated on Nov 22, 2024.
  • Viewing page 1 out of 41 pages.
  • Viewing questions 1-5 out of 203 questions
Get All 203 Questions & Answers
Question No. 1

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor's ask?

Show Answer Hide Answer
Question No. 2

A new company initiates a project to incorporate a cybersecurity team. Which three documents should the risk manager analyze first? (Choose 3)

Show Answer Hide Answer
Correct Answer: A, D, E

Question No. 3

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?

Show Answer Hide Answer
Correct Answer: D
Question No. 4

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Show Answer Hide Answer
Correct Answer: B

Question No. 5

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

Show Answer Hide Answer
Correct Answer: A

A risk trigger is an indication or warning sign that a risk is about to occur or has occurred. A risk trigger can be an event, a condition, or a situation that signals the onset of a risk. A risk trigger can help the project team to identify and respond to risks in a timely manner. In this case, the lack of space to install air conditioners is a risk with high impact on the project. A potential need to share the space with other machinery is an example of an early risk trigger, because it indicates that the space issue may become a problem in the future. If the project team detects this trigger, they can take proactive actions to avoid or mitigate the risk, such as finding an alternative location, modifying the design, or negotiating with the stakeholders.Reference:PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 102-103.


Unlock All Questions for PMI PMI-RMP Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 203 Questions & Answers