Limited-Time Offer: Enjoy 60% Savings! - Ends In 0d 00h 00m 00s Coupon code: 60OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent PMI-RMP Exam Questions & Answers


Prepare for the PMI Risk Management Professional exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the PMI-RMP exam and achieve success.

The questions for PMI-RMP were last updated on Jan 20, 2025.
  • Viewing page 1 out of 41 pages.
  • Viewing questions 1-5 out of 203 questions
Get All 203 Questions & Answers
Question No. 1

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project's risk register and asks the risk manager for an analysis of its effectiveness.

What two actions should the risk manager do next? (Choose two.)

Show Answer Hide Answer
Correct Answer: C, D

The risk manager should first check the risk register for proper risk classification, probability, and impact (C), as these are essential components of an effective risk management process. Next, the risk manager should ensure that the risk origin, triggering events, and ownership are identified (D), as this information helps in assigning responsibilities and taking appropriate actions for each risk. Reference to these steps can be found in the Project Management Institute's (PMI) A Guide to the Project Management Body of Knowledge (PMBOK Guide), Sixth Edition.

The risk manager should check for risk classification and that probability and impact are identified, as these are essential elements of a risk register. Risk classification helps to group risks into categories based on their sources, types, or impacts, which can facilitate risk analysis and response planning. Probability and impact are the two dimensions of risk assessment, which help to measure the likelihood and severity of a risk event, and to prioritize risks based on their significance. The risk manager should also check to ensure that risk origin, triggering event, and ownership is identified, as these are also important components of a risk register. Risk origin refers to the root cause or source of a risk, which can help to understand the nature and characteristics of a risk, and to devise effective risk responses. Triggering event is a specific occurrence or condition that indicates that a risk event has occurred or is about to occur, which can help to monitor and control risks. Ownership is the assignment of a risk to a person or a group who is responsible for managing the risk, which can help to ensure accountability and communication. The risk manager should not check to ensure that the risk is supported by a Monte Carlo simulation, as this is not a mandatory or universal requirement for a risk register. Monte Carlo simulation is a quantitative risk analysis technique that uses computer-generated random scenarios to model the possible outcomes of a project, based on the probability distributions of the input variables. While this technique can provide useful information about the overall project risk exposure and the probability of achieving project objectives, it is not a necessary or sufficient condition for an effective risk register. The risk manager should not check to ensure that the risks are gathered using Delphi technique, as this is also not a compulsory or exclusive requirement for a risk register. Delphi technique is a qualitative risk identification technique that uses a panel of experts to anonymously provide their opinions on potential risks, which are then aggregated and refined through a series of rounds until a consensus is reached. While this technique can help to elicit expert judgment and reduce bias, it is not the only or the best way to identify risks. The risk manager should not check to ensure the risk meeting agenda and supporting documents are distributed, as this is not a relevant or appropriate action for analyzing the effectiveness of a risk register. The risk meeting agenda and supporting documents are part of the risk management plan, which describes how the project team will conduct risk management activities, such as identifying, analyzing, responding, and monitoring risks. The risk meeting agenda and supporting documents are useful for planning and conducting risk meetings, but they are not part of the risk register, which is the output of the risk identification process and the input for the risk analysis and response processes.Reference:PMI. (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition. Chapter 11: Project Risk Management, pp. 395-454. 5


Question No. 2

When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project's contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.

What should the project manager do?

Show Answer Hide Answer
Correct Answer: A

The project's contingency allowance is a provision in the project budget that is intended to cover known risks that may affect the project costs. The risk of increased fuel costs was identified and included in the contingency allowance, so the project manager should use it to process the freight invoices at the actual shipping costs. This is the best way to handle the risk without affecting the project scope, schedule, or quality. Requesting a formal change order from the customer (option B) is not necessary, as the project budget already has a provision for this risk. Processing the freight invoices for the budgeted amount and hoping the shipping company will forgive the difference (option C) is unethical and unprofessional, as it violates the terms of the contract and the PMI Code of Ethics and Professional Conduct. Asking the project sponsor to cover the additional shipping costs on the company's reserves account (option D) is also not appropriate, as the company's reserves are meant for unknown risks that are beyond the project's control, not for known risks that are already accounted for in the project budget.Reference:PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 72; PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 6th ed., 2017, p. 252.

The project manager should use the contingency allowance to cover the additional shipping costs, as it was specifically included in the project budget for such risks. This approach avoids requesting unnecessary changes or relying on external sources to cover the cost overrun.

.


Question No. 3

A risk manager faces resistance as they try to implement the project's risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

Show Answer Hide Answer
Correct Answer: B

When facing resistance from team members, the risk manager should engage in open communication to address their concerns and clarify the importance of risk management in the project.

According to the PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1, the risk manager should handle this situation by meeting with team members to address their concerns. This is because:

Resistance to risk management is a common challenge that can hinder the effectiveness and efficiency of the risk management process. Resistance can stem from various factors, such as lack of awareness, understanding, commitment, trust, or support for risk management; fear of negative consequences or blame; competing priorities or interests; or cultural differences or biases.

Meeting with team members to address their concerns is a proactive and constructive way to overcome resistance and foster a positive risk culture within the project. By meeting with team members, the risk manager can:

Communicate the value and benefits of risk management for the project and the organization, such as improving decision-making, enhancing performance, increasing stakeholder satisfaction, and reducing uncertainty and variability.

Educate and train team members on the risk management principles, processes, tools, and techniques, and how they can be applied to the project context and objectives.

Involve and empower team members in the risk management activities, such as identifying, analyzing, prioritizing, responding, and monitoring risks, and solicit their feedback and suggestions for improvement.

Recognize and reward team members for their contributions and achievements in risk management, and celebrate the successful outcomes and opportunities realized by the project.

The other options are not effective in handling this situation because:

Continuing to implement the risk strategy without addressing the resistance can lead to further conflict, resentment, and distrust among the team members, and undermine the quality and credibility of the risk management process and outputs.

Reducing the number of risk management activities can compromise the project's ability to identify and respond to the risks that may affect its scope, schedule, cost, quality, or other objectives, and expose the project to unnecessary threats or missed opportunities.

Raising the concerns with the project sponsor can escalate the issue and create a negative impression of the team members, and may not resolve the underlying causes of the resistance or improve the team's engagement and commitment to risk management.


PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1

Risk Management Professional (PMI-RMP) Exam Cert Guide2

Question No. 5

After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product's characteristics and quality. What should the risk manager propose to the project manager what to do?

Show Answer Hide Answer
Correct Answer: A

Unlock All Questions for PMI PMI-RMP Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 203 Questions & Answers