Limited-Time Offer: Enjoy 50% Savings! - Ends In 0d 00h 00m 00s Coupon code: 50OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent PMI-SP Exam Dumps

 

Prepare for the PMI Scheduling Professional exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the PMI-SP exam and achieve success.

The questions for PMI-SP were last updated on Feb 21, 2025.
  • Viewing page 1 out of 65 pages.
  • Viewing questions 1-5 out of 326 questions
Get All 326 Questions & Answers
Question No. 1

Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?

Show Answer Hide Answer
Correct Answer: C

According to the PMBOK, Gina will not need the WBS directly, but will rely on the scope baseline.A Work Breakdown Structure (WBS) in project management is a tool that defines a project and groups the project's discrete work elements in

a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. Answer option A is incorrect. The scope baseline is an input to define the project activities. Answer option D is incorrect. Enterprise environmental factors are an input to define the project activities. Answer option B is incorrect. Organizational process assets are an input to define the project activities.


Question No. 2

Frank is the project manager in BlueWell Inc. He is working with his project to subdivide the project work packages into smaller, more manageable components. He and the project team are planning in detail all of the things the team will need to create, purchase, or do in order to satisfy the project scope. Management is concerned with the activity which Frank is using in this scenario, as they believe that Frank is taking too long to complete this pre-execution activity. Which of the following techniques of the activity process is Frank using in this example?

Show Answer Hide Answer
Correct Answer: D

This is an example of decomposition. Frank and the project team are subdividing the work packages

into smaller, more manageable units

called activities.

The tools and techniques used in defining the activity process are as follows:

Decomposition: It is used to further divide the project work package into a more smaller and

convenient form called activities.

Rolling Wave Planning: It is a form of progressive elaboration planning where the work to be

accomplished in the near term is planned

in detail and future work is planned at a higher level of WBS.

Templates: It is an activity list or a part of the activity list taken from the previous project and used in

a new project.

Expert Judgement: The skilled members in a project team or other experts who develop project

scope statements can help provide

knowledge in defining activities.


Question No. 3

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

Show Answer Hide Answer
Correct Answer: B, C, D

Constructability analysis takes into account the location, logistics, resource availability analysis, the average price of general labor in the area, and labor productivity studies from previous similar projects in the area. Constructability analysis is a process that starts in the initial planning phases and persists all over the entire planning cycle and into the implementation phase of the project. Constructability analysis during the planning process examines the methods and cost of installed equipment and materials, technology, site conditions, resources, and related infrastructure. The benefit of constructability analysis is to reduce both the time and cost of a project. Constructability analysis is repeatedly performed throughout the life-cycle of a project in order to optimize cost, plan, and schedule while mitigating risk. It is a very important process that needs to be performed early in planning to allow alternatives to be considered and integrated into the design. Answer option A is incorrect. This comes under the quality assurance phase.


Question No. 4

You have been hired as a contract project manager for Tech Perfect Inc. The project has already been started. Sufficient details of the project have already been structured. You are working with your team for cost estimation of the project. Which of the following estimating techniques will you use for the highest degree of accuracy?

Show Answer Hide Answer
Correct Answer: D

According to the question, you have to use the estimating technique that has a higher

degree of accuracy. The most accurate estimating

technique is bottom-up estimating.

What is bottom-up estimating?

Bottom-up is a cost estimating technique that involves estimating the cost of individual work

packages or schedule

activities with the lowest level of detail. The detailed cost is rolled up (or summarized) to higher

levels for total project

estimates. This summarized data is very useful for reporting and tracking purposes. Bottom-up

estimating provides a

higher degree of accuracy, provided the estimates at the work package level are accurate.

Answer options C, A, and B are incorrect. Parametric modeling and analogous estimating techniques

use top-down estimation model. These

are less accurate than the bottom-up estimation.

What is analogous estimating?

Analogous is an estimating technique that uses the values of parameter, such as scope, cost, budget,

and duration or

measures of scale such as size, weight, and complexity from a previous, similar activity as the basis

for estimation of the

same parameter for a future activity. It is a top-down estimating technique and is a form of expert

judgment. It provides a

lower degree of accuracy than other estimating techniques. This technique is primarily used when

there is a limited amount

of detailed information about the project or program.

What is parametric modeling?

Parametric modeling is an estimating technique that uses parameters, or project characteristics, to

forecast project costs.

It involves a top-down approach and is similar but more accurate than analogous estimating. It uses

historical data and

other variables to calculate an estimate for activity parameters, such as scope, cost, budget, and

duration.


Question No. 5

You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as start- to-start and finish-to-finish successor activities for work that uses particular manufacturing equipment. You explained that the levels of effort activities are maintained for the equipment. This relationship and scheduling scenario is also known as what term?

Show Answer Hide Answer
Correct Answer: B

This is also known as a hammock activity, as the SS and FF relationship hangs off of the

activities in the project network diagram.

A hammock activity is a schedule or project planning term for grouping of subtasks that 'hangs'

between two end dates it is fixed to. It

groups subtasks that are not related in the hierarchical sense of a Work Breakdown Structure. It also

groups subtasks that are not related in

a logical sense of a dependency where one subtask must wait for another.

A hammock activity usually refers to report information that is time-dependent and lasts from the

initial to the latest date of the activities it

encompasses. By using a hammock activity, the top management is able to see an overview of the

project without being besieged by details.

Answer option D is incorrect. Finish-to-start is the most common relationship between project

activities in the project network diagram.

Answer option A is incorrect. Project management overhead describes the work that supports the

project objectives, but is not linked directly

to the project deliverables.

Answer option C is incorrect. A subproject is a discrete set of work that contributes to the project,

but branches off the primary project work. A

subcontract portion of the project is an example of a subproject.


Unlock All Questions for PMI PMI-SP Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 326 Questions & Answers