Limited-Time Offer: Enjoy 60% Savings! - Ends In 0d 00h 00m 00s Coupon code: 60OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent PMI-SP Exam Questions & Answers


Prepare for the PMI Scheduling Professional exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the PMI-SP exam and achieve success.

The questions for PMI-SP were last updated on Dec 21, 2024.
  • Viewing page 1 out of 65 pages.
  • Viewing questions 1-5 out of 326 questions
Get All 326 Questions & Answers
Question No. 1

Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below: Measurements Values BCWP (or EV)425 BCWS (or PV) 400 ACWP (or AC)510 What is the schedule performance index (SPI) of the project at the current point of time?

Show Answer Hide Answer
Correct Answer: C

According to the question, you are required to calculate the schedule performance

index (SPI) of the project. Schedule performance index

(SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future

performance. SPI is the ratio of earned

value to planned value. The SPI is calculated based on the following formula:

SPI = Earned Value (EV) / Planned Value (PV)

If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value

is less than 1, it shows poor

performance. The SPI value of 1 indicates that the project is right on target. Here, SPI is calculated as

follows:

SPI = EV / PV

= 425/400

= 1.0625

As the SPI (1.0625) is greater than 1, it shows that the schedule performance is better than

expected.

What is BCWP (or EV)?

Budgeted cost of work performed (BCWP) or Earned Value (EV) is the value of completed work. It is

the budgeted amount

for the work actually completed on the schedule activity during a given time period.

What is BCWS (or PV)?

Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV) is the authorized budget assigned

to the scheduled work

to be accomplished for a schedule activity or Work Breakdown Structure (WBS) component.

What is ACWP (or AC)?

Actual cost of work performed (ACWP) or Actual Cost (AC) is the total costs actually incurred and

recorded in accomplishing

work performed during a given time period for a schedule activity. It is the cost of the work to date,

including direct and

indirect costs. AC is money that has actually been expended to date.


Question No. 2

You are project manager of HHK project. Examine the network diagram given below:

A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?

Show Answer Hide Answer
Correct Answer: A

Activity E has four days of float. The entire project will take 19 days to complete. Float,

also called slack, is the amount of time an activity can

be delayed without affecting any subsequent activities. There are two types of floats available:

Free Float: It is the amount of time a schedule activity can be delayed without delaying the early

start date of any immediately

following schedule activities.

Total Float: It is the total amount of time that a schedule activity may be delayed from its early start

date without delaying the project

finish date, or violating schedule constraint.

Float is calculated by using the critical path method technique.

Answer option D is incorrect. Activity E is not on the critical path.

Answer options C and B are incorrect. These are incorrect calculations of the amount float available

for Activity E.


Question No. 3

Harry works as a project manager for BlueWell Inc. He is determining the budget of the project.

According to the PMBOK, there are seven

inputs to this process. Which one of the following is NOT an input to the determine budget process?

Show Answer Hide Answer
Correct Answer: B

Reserve analysis is not an input to the determine budget process. It is a technique used

for determining the budget.

The inputs to the determine budget process are as follows:

Activity cost estimates

Basis of estimates

Scope baseline

Project schedule

Resource calendars

Contracts

Organizational process assets


Question No. 4

You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special hardware to electronically lock and open the doors. You've gathered the project team before they begin the installation for a hands-on training. As a group you and the project team install 50 doors following a checklist of instructions so that every door will be installed exactly the same throughout the campus and with minimal waste. This is an example of what project execution technique?

Show Answer Hide Answer
Correct Answer: A

This is an example of a preventive action as you're working with the team before they install the doors to train them on the installation. The checklist is a quality control tool but the question was asking for a project execution activity. Preventive and corrective actions are part of project execution. Answer option D is incorrect. Quality control is a controlling and monitoring process, not an executing process. Answer option B is incorrect. The defect repair validation comes after the project team has corrected an error - something that has not occurred in this instance. Answer option C is incorrect. Corrective action is a response to something that needs to be corrected in the project.


Question No. 5

John works as a project manager for BlueWell Inc. His project has a budget of $795,000 and he has

spent $325,000 on the project. But, he has completed only 40 percent of the project work till now.

Management wants to know what the project's cost performance index is. What value will John

report?

Show Answer Hide Answer
Correct Answer: D

Cost performance index (CPI) is used to calculate performance efficiencies. It is used in

trend analysis to predict future performance. CPI is the

ratio of earned value to actual cost. The CPI is calculated based on the following formula:

CPI = Earned Value (EV) / Actual Cost (AC)

If the CPI value is greater than 1, it indicates better than expected performance, whereas if the value

is less than 1, it shows poor

performance. The CPI value of 1 indicates that the project is right on target. In this instance, it's

EV = 0.40 * 750,000

= 300,000

CPI = EV/AC

= 300,000/325,000

= 0.92


Unlock All Questions for PMI PMI-SP Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 326 Questions & Answers