Limited-Time Offer: Enjoy 60% Savings! - Ends In 0d 00h 00m 00s Coupon code: 60OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent PMI-SP Exam Questions & Answers


Prepare for the PMI Scheduling Professional exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the PMI-SP exam and achieve success.

The questions for PMI-SP were last updated on Jan 17, 2025.
  • Viewing page 1 out of 65 pages.
  • Viewing questions 1-5 out of 326 questions
Get All 326 Questions & Answers
Question No. 1

You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will you record for this activity?

Show Answer Hide Answer
Correct Answer: A

This is an example of a three-point estimate. A three-point estimate records the optimistic, most likely, and the pessimistic duration, and then records an average for the predicted duration Three-point estimate is a way to enhance the accuracy of activity duration estimates. This concept is originated with the Program Evaluation and Review Technique (PERT). PERT charts the following three estimates:

Most likely (TM): The duration of activity based on realistic factors such as resources assigned, interruptions, etc. Optimistic (TO): The activity duration based on the best-case scenario Pessimistic (TP): The activity duration based on the worst-case scenario The expected (TE) activity duration is a weighted average of these three estimates: TE = (TO + 4TM + TP) / 6 Duration estimates based on the above equations (sometimes simple average of the three estimates is also used) provide more accuracy. It can be calculated as follows: TE = ( 20 + 45*4 + 90) / 6 = 290/6 =48 Answer options B, C, and D are incorrect. These are not the valid answers for this question.


Question No. 2

Mark works as a project manager for Blue Well Inc. He is making relevant information available to the project stakeholders as required. According to Mark, which of the following are NOT the tools and techniques of the Distribute Information process?

Show Answer Hide Answer
Correct Answer: A, D

These tools and techniques are used in the Plan communications process.

The tools and techniques used in the Distribute information process are as follows:

Communication methods: These methods includes individual and group meetings, computer chats,

audio and video conferences and

other remote communications methods to distribute information.

Information distribution tools: Various information distribution tools can be used to distribute

information such as electronic tools,

electronic conferencing tools, hard copy document distribution etc.


Question No. 3

You are the project manager of the GHY Project. This project is scheduled to last for one year and

has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are up

posed to be at your second milestone which accounts for half of the project completion. There have

been some errors in the project which has caused you to spend $2,073,654. What is this project's

schedule variance?

Show Answer Hide Answer
Correct Answer: C

The schedule variance can be found by subtracting the planned value from the earned

value. In this instance, it is $2,025,000 minus

$2,250,000.

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead or behind what

was planned for this period in time. The schedule variance is calculated based on the following

formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the project is ahead of

the planned schedule. A value of 0 indicates that the project is right on target.

Answer option B is incorrect. This is the cost variance for the project.

Answer option A is incorrect. 10 percent is not a valid answer.

Answer option D is incorrect. This is not a valid variance for this question; variances are typically

negative numbers.


Question No. 4

Beth is the project manager of the KJH project. Sarah is Beth's administrative assistant and Ben is the project team leader. Beth's project has eight virtual teams throughout the world that will be working on the activities relevant to the deliverables in their locales. Thomas, the project sponsor, has told Beth that he is to be kept abreast of all communication between her project and the stakeholders. In this project, who is the lead person responsible for communication with all stakeholders?

Show Answer Hide Answer
Correct Answer: D

Beth, the project manager, is responsible for communication with all stakeholders. According to the

PMBOK, the project manager occupies the

center of the interactions between stakeholders and the project itself.

Answer option B is incorrect. Sarah may help with the communications, but she is not responsible

for the communications.

Answer option A is incorrect. Thomas, the project sponsor, just needs to be kept abreast of the

information.

Answer option C is incorrect. The project team leaders for the virtual sites are not responsible for

communicating with the project

stakeholders.


Question No. 5

John works as a project manager for BlueWell Inc. His project has a budget of $795,000 and he has

spent $325,000 on the project. But, he has completed only 40 percent of the project work till now.

Management wants to know what the project's cost performance index is. What value will John

report?

Show Answer Hide Answer
Correct Answer: D

Cost performance index (CPI) is used to calculate performance efficiencies. It is used in

trend analysis to predict future performance. CPI is the

ratio of earned value to actual cost. The CPI is calculated based on the following formula:

CPI = Earned Value (EV) / Actual Cost (AC)

If the CPI value is greater than 1, it indicates better than expected performance, whereas if the value

is less than 1, it shows poor

performance. The CPI value of 1 indicates that the project is right on target. In this instance, it's

EV = 0.40 * 750,000

= 300,000

CPI = EV/AC

= 300,000/325,000

= 0.92


Unlock All Questions for PMI PMI-SP Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 326 Questions & Answers