Limited-Time Offer: Enjoy 50% Savings! - Ends In 0d 00h 00m 00s Coupon code: 50OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent PMI PMP Exam Dumps

 

Prepare for the PMI Project Management Professional (2024) exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the PMI PMP exam and achieve success.

The questions for PMP were last updated on Apr 1, 2025.
  • Viewing page 1 out of 341 pages.
  • Viewing questions 1-5 out of 1707 questions
Get All 1707 Questions & Answers
Question No. 1

A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?

Show Answer Hide Answer
Question No. 2

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.

What should the project manager do next?

Show Answer Hide Answer
Correct Answer: C

When a risk that has been previously identified occurs, the project manager should consult the risk register to determine the planned responses for this risk event. The risk register contains the details of risk responses that are planned for the identified risks, including contingency plans and fallback plans. Implementing the planned risk response is crucial to manage the risk effectively and keep the project on track. This approach is aligned with the PMI's guidelines on risk management, which emphasize the importance of preparing for and responding to risks proactively.Reference: (Project Management Professional (PMP) Reference Materials source and documents; Professional in Business Analysis Reference Materials source and documents)


Question No. 3

A project manager has been assigned as the servant leader for an ongoing project that historically has presented unexpected problems. The main stakeholder is hesitant to continue with the rest of the sprints even though there are no open issues or indications of risks at this stage.

What should the project manager do to address this problem?

Show Answer Hide Answer
Question No. 4

A project manager is assigned to a yearlong project. Before the start of the design phase, a competitor announces that they will release a similar deliverable in 8 months, although with fewer features and functionality.

Which two actions should the project manager take next? (Choose 2)

Show Answer Hide Answer
Correct Answer: C, D

When faced with the competitor's announcement, the project manager should take the following actions:

1. Reduce Scope Items: Given the competitor's shorter timeline and fewer features, the project manager should reevaluate the project scope. Reducing the scope items of the final deliverable allows the project team to focus on essential features and deliver a more streamlined product within the available time frame.

2. Discuss External Risk with Project Sponsor: The project manager should engage


Question No. 5

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

Show Answer Hide Answer
Correct Answer: C

According to the PMBOK Guide, one of the key inputs to the develop project team process is the training needs assessment, which identifies the gaps between the current and desired competencies of the project team members1.The project manager should assess the training requirements and ensure time for professional development training by senior members, as this is a way of enhancing the skills and knowledge of the team members, improving their performance, and increasing their motivation and satisfaction2.This option is also aligned with the Professional in Business Analysis (PMI-PBA) Guide, which states that the business analyst should identify and address the training needs of the project team and stakeholders3. The other options are not appropriate, as they do not address the root cause of the problem, which is the lack of experience and competence of the team members. Increasing the overall project duration may not improve the quality of the project deliverables, and may also increase the project costs and risks. Replacing or removing team members may not be feasible or desirable, as it may disrupt the team dynamics, cause resentment, and create additional work for the project manager.Moreover, these options do not consider the potential of the team members to learn and grow in their roles.Reference:1: PMBOK Guide, 6th edition, page 3492: Project Team Training: Proven Key to Organizational Teamwork43: Professional in Business Analysis (PMI-PBA) Guide, 2nd edition, page 97.


Unlock All Questions for PMI PMP Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 1707 Questions & Answers