Handsome Savings - Limited Time Offer 30% OFF - Ends In 0d 0h 0m 0s Coupon code: 50OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

PMI PMP Exam Actual Questions

The questions for PMP were last updated on Oct 4, 2024.
  • Viewing page 1 out of 74 pages.
  • Viewing questions 1-5 out of 369 questions
Unlock Access to All 369 Questions & Answers
Question No. 1

Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the

scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively, among other critical blockers.

What should the project manager do?

Show Answer Hide Answer
Correct Answer: B

Question No. 3

After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session

What should the project manager do first?

Show Answer Hide Answer
Correct Answer: A

Question No. 4

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

Show Answer Hide Answer
Correct Answer: D

Question No. 5

A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress, and points to the project manager.

What should the project manager do?

Show Answer Hide Answer
Correct Answer: C

A project manager is managing a project for a government owned company using an iterative approach. The first useful release to production consisted of three iterations. Each iteration was

successfully checked by the client's representatives in the test environment. However, when the team started deploying to the production environment, the security team declined it.

What should the project manager have done to prevent this?

Deployed to production after the first iteration

Planned smaller iterations to review the results more often

Reviewed the compliance requirements with stakeholders

Implemented the authorization in the first iteration

The project manager should have reviewed the compliance requirements with stakeholders before starting the project, as well as during each iteration. Compliance requirements are the rules and regulations that the project must follow, such as security, health and safety, regulatory compliance, etc. By reviewing the compliance requirements with stakeholders, the project manager can ensure that the project aligns with the expectations and needs of the client, the government, and the organization. This can also help to identify and mitigate any potential threats or risks to compliance, and avoid any consequences of noncompliance, such as delays, rework, penalties, or loss of reputation.Reference:Project Management Professional (PMP) Certification | PMI,My project should be compliant - Project Management Institute,3.1. Plan and manage project compliance - KnowledgeMap


Product Image

Unlock All Questions for PMI PMP Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 369 Questions & Answers