Limited-Time Offer: Enjoy 60% Savings! - Ends In 0d 00h 00m 00s Coupon code: 60OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent PMI PMP Exam Questions & Answers


Prepare for the PMI Project Management Professional (2024) exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the PMI PMP exam and achieve success.

The questions for PMP were last updated on Dec 21, 2024.
  • Viewing page 1 out of 341 pages.
  • Viewing questions 1-5 out of 1707 questions
Get All 1707 Questions & Answers
Question No. 1

A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.

What should the project manager do next?

Show Answer Hide Answer
Correct Answer: B

The best course of action when receiving a request for a more detailed project status is to engage in a dialogue with the senior manager to understand their specific needs. This approach aligns with the PMBOK Guide's emphasis on effective communication and stakeholder engagement as key aspects of project management. By discussing the requirements directly, the project manager can tailor the communication to provide relevant and precise information that satisfies the senior manager's request without overwhelming them with unnecessary details. This method ensures that the project manager is responsive to stakeholder needs and maintains clear and open lines of communication.


Question No. 2

Close to the end of a project, a customer claims that some deliverables have not

been met and starts initiating change requests. What should the project manager do next?

Show Answer Hide Answer
Question No. 3

A project manager has been assigned as the servant leader for an ongoing project that historically has presented unexpected problems. The main stakeholder is hesitant to continue with the rest of the sprints even though there are no open issues or indications of risks at this stage.

What should the project manager do to address this problem?

Show Answer Hide Answer
Question No. 4

A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.

How should the project manager handle this issue?

Show Answer Hide Answer
Correct Answer: C

According to the PMBOK Guide Seventh Edition, one of the project management principles is to engage stakeholders actively and frequently. This means that the project manager should identify and analyze the needs, expectations, and interests of all stakeholders, and involve them appropriately throughout the project life cycle. The stakeholder register is a document that lists the key stakeholders, their roles, responsibilities, and level of influence on the project. The stakeholder engagement plan is a document that describes the strategies and actions to communicate with, manage, and influence the stakeholders.

In this scenario, the project manager has discovered that the local community was not included in the stakeholder register, which has caused them to oppose the project. This is a serious issue that can affect the project's performance, reputation, and acceptance. Therefore, the project manager should not disregard these stakeholders, as this would violate the principle of stakeholder engagement and potentially escalate the conflict. The project manager should also not just explain to the community members why they were not included as stakeholders, as this would not address their concerns or expectations. The best option is to update the stakeholder register and revise the stakeholder engagement plan, as this would allow the project manager to acknowledge the community as a stakeholder, assess their impact and interest, and develop appropriate strategies and actions to engage them effectively and proactively.Reference:

PMBOK Guide Seventh Edition, page 9

Project Management Principles 9-12, Episode 479: Project Management Principles 9-12 (Free)


Question No. 5

The portfolio management office wants to cut costs by suspending some ongoing

projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio

management office has not backed down on their plan.

What should the project manager do to continue the project?

Show Answer Hide Answer
Correct Answer: C

According to the PMBOK Guide, the portfolio management office (PMO) is responsible for ensuring that the projects and programs within the portfolio are aligned with the organizational strategy and objectives. The project manager should demonstrate the project alignment to the organizational strategy by showing how the project delivers value and benefits to the organization and its stakeholders. This may include presenting the project business case, benefits management plan, stakeholder analysis, and other relevant documents that justify the project's existence and contribution. Demonstrating the project alignment to the organizational strategy is the best way to continue the project and avoid suspension by the PMO. Meeting with the project team and revising the project goals (A) may not be effective if the project is already in alignment with the organizational strategy and the PMO is not aware of it. Updating the project charter to make it align with organizational strategy (B) may not be feasible or ethical if the project charter has already been approved and authorized by the project sponsor and other key stakeholders. Escalating the issue with the project sponsor to request support (D) may be a possible action, but not the best one, as it may create conflict or resentment between the project sponsor and the PMO. The project manager should first try to resolve the issue with the PMO directly by demonstrating the project alignment to the organizational strategy.Reference: PMBOK Guide, 6th edition, pages 33-34, 75-76, 129-130.


Unlock All Questions for PMI PMP Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 1707 Questions & Answers