Limited-Time Offer: Enjoy 60% Savings! - Ends In 0d 00h 00m 00s Coupon code: 60OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent SAP C_ACT_2403 Exam Questions & Answers


Prepare for the SAP Certified Associate - Project Manager - SAP Activate exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the SAP C_ACT_2403 exam and achieve success.

The questions for C_ACT_2403 were last updated on Nov 22, 2024.
  • Viewing page 1 out of 16 pages.
  • Viewing questions 1-5 out of 80 questions
Get All 80 Questions & Answers
Question No. 1

What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Correct Answer: B, D

The product owner's responsibilities include defining objectives for each release to align with business goals and prioritizing backlog items by business priority to ensure high-value deliverables are completed first. While the team estimates user stories, the product owner ensures clarity and prioritization.


Question No. 2

In which workstream do you execute an organizational change impact analysis?

Show Answer Hide Answer
Correct Answer: B

Organizational change impact analysis is conducted within the Solution Adoption workstream. This analysis assesses the impact of changes on the organization and supports change management activities to ensure successful adoption.


Question No. 3

You are implementing SAP S/4HANA Cloud, public edition for your customer. How do you activate the pre-configuration?

Show Answer Hide Answer
Correct Answer: C

Pre-configuration for SAP S/4HANA Cloud, public edition, is activated via the Central Business Configuration system, which centralizes and streamlines the configuration process for SAP Cloud solutions.


Question No. 4

Which of the following Accelerators can you find in the SAP Signavio Process Navigator? Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Correct Answer: A, C

SAP Signavio Process Navigator provides accelerators like Process Diagrams for visualizing workflows and Test Scripts for validating process steps, supporting the analysis and configuration of business processes in SAP implementations.


Question No. 5

You are transitioning to SAP S/4HAN

Show Answer Hide Answer
Correct Answer: A, A

Custom code adjustments are typically made in the Realize phase, where the system configuration and development activities take place. This phase involves adapting custom code to align with SAP S/4HANA's updated architecture and functionalities.