Handsome Savings - Limited Time Offer 30% OFF - Ends In 0d 0h 0m 0s Coupon code: 30OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

SAP C_ACT_2403 Exam Actual Questions

The questions for C_ACT_2403 were last updated on Sep 16, 2024.
  • Viewing page 1 out of 16 pages.
  • Viewing questions 1-5 out of 82 questions
Unlock Access to All 82 Questions & Answers
Question No. 1

Which of the following steps are part of the fit-to-standard process? Note: There are 2 correct answers to this question.

Show Answer Hide Answer
Correct Answer: B, D

B is correct because reviewing Best Practices process flow is one of the steps that are part of the fit-to-standard process. The Best Practices process flow is a diagram that shows the standard SAP functionality and configuration for a scope item. The project team reviews the Best Practices process flow with the customer to demonstrate how the solution supports their business processes, and to identify any gaps or extensions that need to be addressed.

D is correct because enabling customers on standard business processes is one of the steps that are part of the fit-to-standard process. The project team enables customers on standard business processes by providing them with access to a starter system, where they can explore and test the predefined configuration and sample data for each scope item. The project team also provides customers with training materials and guidance on how to use the solution. Verified Reference:

: [SAP Activate Methodology for SAP S/4HANA Cloud], page 18

: [SAP Activate -- Explore Phase: Use Fit-to-Standard to Confirm Business Process Fit and Identify Gaps in Your SAP S/4HANA Cloud Implementation]


Question No. 2

Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?

Show Answer Hide Answer
Correct Answer: A

A is correct because Planning poker is an estimation technique that you can use in an Agile delivery approach to size the user stories during sprint planning. Planning poker is a game where each team member uses a set of cards with numbers that represent the relative effort of a user story. The team members reveal their cards simultaneously and discuss their estimates until they reach a consensus. This technique is based on the concept of story points, which are units of measure for expressing the overall effort required to fully implement a user story. Story points are assigned to user stories based on their complexity, risk, and uncertainty. Verified Reference:

: Planning Poker


Question No. 3

Which of the following is a key characteristic of the Agile project approach?

Show Answer Hide Answer
Correct Answer: C

C is correct because Iterative build with frequent inspections is a key characteristic of the Agile project approach. The Agile project approach follows an iterative and incremental development process, where the solution is built and delivered in small increments called sprints. Each sprint consists of planning, designing, building, testing, and reviewing activities, where the team inspects the solution and adapts to changing requirements and feedback. Verified Reference:

: What is Agile Software Development?


Question No. 4

What is the objective of using scaling Scrum techniques when coordinating large teams in complex projects?

Show Answer Hide Answer
Correct Answer: C

C is correct because ensuring alignment in architecture, configuration, and integration is one of the objectives of using scaling Scrum techniques when coordinating large teams in complex projects. Scaling Scrum techniques are methods that help to apply Scrum principles and practices across multiple teams working on a large-scale product or program. Scaling Scrum techniques aim to ensure alignment in architecture, configuration, and integration by establishing a common vision, backlog, definition of done, and cadence for the teams, and by facilitating cross-team communication and collaboration


Question No. 5

Who determines the tasks that are required to complete the committed backlog items in a Sprint?

Show Answer Hide Answer
Correct Answer: A

A is correct because the Scrum team is the one that determines the tasks that are required to complete the committed backlog items in a Sprint. The Scrum team is a self-organizing and cross-functional group of people who work together to deliver a potentially releasable increment of the product at the end of each Sprint. The Scrum team breaks down the user stories into smaller and manageable tasks, and assigns them to the team members based on their skills and availability.


Product Image

Unlock All Questions for SAP C_ACT_2403 Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 82 Questions & Answers