Prepare for the SAP Certified Associate - SAP S/4HANA Asset Management exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.
QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the SAP C_S43_2022 exam and achieve success.
Which requirements have to be fulfilled so that an Inspection Checklist with Inspection Lots is generated? Note: There are 2 correct answers to this question.
What do you have to consider when implementing Ul technologies in SAP S/4HANA Asset Management? Note: There are 2 correct answers to this question
When implementing UI technologies in SAP S/4HANA Asset Management, you have to consider the following points:
You want to assign components to a General Maintenance Task List. What are prerequisites for assigning material components to a task list operation? Note: There are 2 correct answers to this question
You want to have several plan dates calculated in a maintenance plan.Which scheduling parameter do you use?
To have several plan dates calculated in a maintenance plan, you use the scheduling period parameter. The scheduling period defines the time interval for which the system calculates the planned dates for the maintenance plan. For example, if you enter 12 months as the scheduling period, the system calculates the planned dates for the next 12 months from the current date. You can also specify the end date for scheduling, which is the last date for which the system calculates the planned dates. The scheduling indicator determines how the system calculates the planned dates based on the cycle, the shift factor, and the tolerance. The call horizon defines the percentage of the cycle that must be expired before the system generates a call object (such as a maintenance order or notification) for the planned date.
How does the work center influence cost calculation in the maintenance order? Note: There are 2 correct answers to this question
The work center influences cost calculation in the maintenance order via the cost center and activity type, and via the activity type and hourly rate. The cost center and activity type are assigned to the work center in the master data, and they determine the planned costs of the work center. The activity type and hourly rate are used to calculate the actual costs of the work center based on the actual hours reported for the maintenance order operations.
Option A (Via cost center assigned to a personnel number) is incorrect, because the cost center assigned to a personnel number is not relevant for the cost calculation of the work center. Option C (Via organizational unit and personal hourly rate) is also incorrect, because the organizational unit and personal hourly rate are not used to calculate the costs of the work center.
References:
Cost Centers and Activity Types
Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits
Get All 80 Questions & Answers