Most Recent SAP C_TS410_2022 Exam Questions & Answers


Prepare for the SAP Certified Application Associate - Business Process Integration with SAP S/4HANA exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the SAP C_TS410_2022 exam and achieve success.

The questions for C_TS410_2022 were last updated on Nov 22, 2024.
  • Viewing page 1 out of 16 pages.
  • Viewing questions 1-5 out of 80 questions
Get All 80 Questions & Answers
Question No. 1

What occurs when a maintenance technician changes the status of an order to technically completed? Note: There are 3 correct answers to this question

Show Answer Hide Answer
Correct Answer: B, C, D

Technical Completion of Maintenance Order: When a maintenance order is set to technically completed (TECO), it signifies that the physical work is finished, but there might still be administrative tasks to complete.

Effects of TECO:

B . Incoming Invoices: Even after TECO, the system allows processing of incoming invoices related to the order, ensuring financial transactions can be completed.

C . Purchase Requisitions: Open purchase requisitions linked to the order are automatically marked for deletion, preventing unnecessary procurement.

D . Material Reservation: Materials reserved for the order are released, making them available for other orders or operations.

Implementation in SAP S/4HANA:

Change the status of the maintenance order to TECO in the Plant Maintenance (PM) module.

Verify the automatic processing of invoices, deletion flags on purchase requisitions, and the release of reserved materials.


SAP Plant Maintenance Guide

SAP S/4HANA Asset Management Documentation

Question No. 2

Which business process activities create a Financial Accounting (FI) document? Note: There are 3 correct answers to this question

Show Answer Hide Answer
Correct Answer: B, C, E

Business process activities that create a Financial Accounting (FI) document include Post Goods Issue to a Production Order (B), Execute a Depreciation Run (C), and Transfer Stock to Another Company Code (E). These transactions directly impact financial accounts, such as inventory, cost of goods sold, asset accounts, and intercompany accounts, resulting in the generation of FI documents. Reference = SAP Financial Accounting (FI) and Controlling (CO) documentation.


Question No. 3

Which controlling objects can be settled by a settlement rule in SAP S/4HANA? Note: There are 3 correct answers to this question

Show Answer Hide Answer
Correct Answer: A, B, C

Controlling objects that can be settled by a settlement rule in SAP S/4HANA include Production Orders (A), Maintenance Orders (B), and WBS Elements (C). Settlement rules define how costs collected on these objects are allocated to other cost receivers, such as cost centers, projects, or fixed assets, for accurate cost tracking and analysis. Reference = SAP Controlling (CO) and Project System (PS) documentation.


Question No. 4

What data must be linked to a cost center to derive segment accounting?

Show Answer Hide Answer
Correct Answer: A

Segment Reporting and Profit Centers: For segment reporting in SAP, a profit center is used to track the financial performance of different business segments. Linking a cost center to a profit center allows for detailed financial analysis and segment reporting.

Implementation and Configuration:

Assign Profit Centers: In the master data of a cost center, assign a profit center to ensure financial transactions related to the cost center can be attributed to the correct business segment.

Segment Reporting: Utilize this setup for segment reporting in financial statements, enhancing transparency and control over segment-wise performance.

Financial Integration:

The linkage between cost centers and profit centers is crucial for deriving segment accounting information, facilitating the allocation of costs and revenues to different business segments.


SAP Financials Configuration Guide

SAP Profit Center Accounting Documentation

Question No. 5

You have created an equipment master record. What other master data record can be created automatically?

Show Answer Hide Answer
Correct Answer: C

When you create an equipment master record in SAP, it is possible to automatically create an Asset master record (C) linked to that piece of equipment. This integration allows for seamless asset management, enabling financial tracking and depreciation calculations for the equipment as a fixed asset within the organization's asset accounting processes.

A Functional Location (A) represents the place where an equipment is installed and is not automatically created from an equipment master but rather associated with it.

A Material (B) record represents items that can be procured, stored, and sold and is not automatically created from an equipment master.

A Maintenance BOM (Bill of Materials) (D) details the components that make up a piece of equipment or assembly but must be created separately and then associated with the equipment.


Unlock All Questions for SAP C_TS410_2022 Exam

Full Exam Access, Actual Exam Questions, Validated Answers, Anytime Anywhere, No Download Limits, No Practice Limits

Get All 80 Questions & Answers