Prepare for the Scaled Agile SSM (6.0) - SAFe Scrum Master exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.
QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the Scaled Agile SSM exam and achieve success.
What is one benefit of PI Planning?
One benefit of PI Planning is that it allows for faster decision-making by bringing together all the members of the Agile Release Train (ART) and the relevant stakeholders in a face-to-face (or virtual) event. PI Planning provides an opportunity for the ART to align on a common vision and mission, review the business context and priorities, identify and resolve dependencies and risks, and commit to a realistic and achievable plan for the next Program Increment (PI). By having everyone involved in the planning process, the ART can leverage the collective knowledge and expertise of the participants, reduce ambiguity and uncertainty, and make informed and timely decisions that support the delivery of value to the customers. (Must be taken from SAFe 6 Scrum Master resources)
PI Planning - Scaled Agile Framework
Planning Interval (PI) - Scaled Agile Framework
Preparing for PI Planning | Checklist for Scrum Masters and Product ...
What is the first step of the problem-solving workshop?
The first step of the problem-solving workshop is to agree on the problem to solve. This step is important because it helps the teams to clearly state the problem, highlight the what, where, when, and impact of the problem, and avoid addressing the symptoms instead of the root causes. By agreeing on the problem to solve, the teams can focus their investigation and analysis, and save time and effort. The problem statement should be succinct and specific, and should not include any assumptions or solutions.
Inspect and Adapt - Scaled Agile Framework
What is the intended value of the Backlog Refinement event?
According to SAFe, which of the following metrics are reported at the Inspect and Adapt event?
According to the SAFe 6 Scrum Master documentation, one of the metrics that are reported at the Inspect and Adapt event is the ART predictability measure. This metric shows how well the ART delivers on its PI objectives, which are the SMART commitments made by the teams during PI planning. The ART predictability measure is calculated by dividing the total actual business value achieved by the total planned business value, as shown in the PI system demo. The ART predictability measure helps the ART to assess its performance, identify gaps, and improve its forecasting accuracy and reliability. (Must be taken from SAFe 6 Scrum Master resources)
What is one element on the Scrum Master/Team Coach responsibility wheel?
Helping the team prepare for the event, such as reviewing the business context, vision, and backlog, and creating draft plans
Supporting the team during the event, such as facilitating breakout sessions, resolving issues, and ensuring alignment and collaboration with other teams
Assisting the team after the event, such as finalizing the plans, updating the PI board, and conducting a retrospective
Facilitating PI Planning is one of the ways the Scrum Master/Team Coach helps the team and the ART achieve their goals and deliver value. (Must be taken from SAFe 6 Scrum Master resources)