QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the Scrum PSM-I exam and achieve success.
When many Development Teams are working on a single product, what best describes the definition of ''Done''? (Choose the best answer.)
When many Development Teams are working on a single product, the definition of ''Done'' must be shared by all Development Teams and make their combined work potentially releasable, as stated in [4]: ''When multiple teams work together on one product they must mutually define and comply with the same Definition of Done. This makes sure all Increments adhere to a consistent quality level.''
You are the Scrum Master on a newly formed Scrum Team. Which three of the following activities would probably help the team in starting up? (Choose three.)
The correct answers are B, E, and F, because these activities would probably help the team in starting up. Having the Scrum Team members introduce themselves and give a brief background of their skills and work history helps build trust and rapport among them. Ensuring the team understands they need a definition of ''Done'' helps create transparency and alignment on the quality standards for the product. Asking the Product Owner to discuss the product or project, its history, goals, and context, as well as answer questions helps clarify the vision and value of the product.
A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give? (Choose the best answer.)
According to the Scrum Guide, estimates are made by the people doing the work, which is the Development Team. The Development Team is responsible for all estimates in the Product Backlog and the Sprint Backlog. The other options are not valid guidelines for estimating work in Scrum, as they are either too prescriptive (such as requiring story points or relative units), incorrect (such as forbidding estimating or having the Product Owner make estimates), or unnecessary (such as checking estimates with the Development Team).
Which three of the following are time-boxed events in Scrum? (Choose three.)
Sprint Planning (eight hours or less for a one-month Sprint)
Daily Scrum (15 minutes or less for a one-month Sprint)
Sprint Review (four hours or less for a one-month Sprint)
Sprint Retrospective (three hours or less for a one-month Sprint)
The other options are not time-boxed events in Scrum.
A properly functioning Scrum Team will have at least one Release Sprint and may well have several.