Most Recent ServiceNow CIS-SPM Exam Dumps

 

Prepare for the ServiceNow Certified Implementation Specialist - Strategic Portfolio Management exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the ServiceNow CIS-SPM exam and achieve success.

The questions for CIS-SPM were last updated on Mar 30, 2025.
  • Viewing page 1 out of 12 pages.
  • Viewing questions 1-5 out of 60 questions
Get All 60 Questions & Answers
Question No. 1

What is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later?

Show Answer Hide Answer
Correct Answer: C

A baseline is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later. A baseline captures the original plan of the project and allows you to track the changes and deviations from the plan over time. You can create multiple baselines for a project and compare them with the current state of the project. You can find more information about baselines in theProduct Documentationfor ServiceNow.


Question No. 2

The RIDAC workflow can be modified by using which recommended feature?

Show Answer Hide Answer
Correct Answer: A

According to theRIDAC (Risk, Issue, Decision, Action, and Request Changes) record entries for a projectdocument, the RIDAC workflow can be modified by using the Workflow Editor, which is a graphical tool that allows you to create and edit workflows. The other options are not correct, as they are not recommended features for modifying the RIDAC workflow. The Project Form is used to create and update project records. The Flow Designer is used to automate processes without coding. The Service Catalog is used to order items and services.


Question No. 3

What is a resource event?

Show Answer Hide Answer
Correct Answer: B

A resource event is a non-scheduled activity that affects the availability and capacity of a resource or a group of resources. Examples of resource events are vacations, holidays, training, or sick leave. Resource events can be created by resource managers or resources themselves, and they can be viewed in the resource calendar or the resource workbench. You can find more information about resource events in theProduct Documentationfor ServiceNow.


Question No. 4

Which of the following can be used to calculate planned cost when creating a resource plan?

Choose 2 answers

Show Answer Hide Answer
Correct Answer: B, D

According to the ServiceNow documentation1, a rate card is a table that defines the hourly cost of labor for different roles or resources. A project rate is a fixed rate that is applied to all resources assigned to a project, regardless of their roles or individual rates. Both of these can be used to calculate the planned cost of a resource plan by multiplying the hours allocated to each resource by the corresponding rate. The other options are incorrect because:

A) Demand rate: A demand rate is a rate that is applied to a demand, not a resource plan.It is used to estimate the cost of fulfilling a demand before it is converted into a project2.

C) Default rate: A default rate is a rate that is applied to a resource when no other rate is specified.It is not a valid option for calculating the planned cost of a resource plan, as it is only used as a fallback option3.

1: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/concept/c_RateCards.html2: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_DemandRate.html3: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/concept/c_DefaultRate.html


Question No. 5

The Project management application supports two types of external dependencies. What are they?

Choose 2 answers

Show Answer Hide Answer
Correct Answer: A, D

The Project Management application supports two types of external dependencies: hard dependency and soft dependency. A hard dependency is a dependency that must be met before a task can start or finish. A soft dependency is a dependency that is preferred but not mandatory for a task to start or finish. You can find more information about these dependency types in theProduct Documentationfor ServiceNow.