Limited-Time Offer: Enjoy 50% Savings! - Ends In 0d 00h 00m 00s Coupon code: 50OFF
Welcome to QA4Exam
Logo

- Trusted Worldwide Questions & Answers

Most Recent US Green Building Council LEED-AP-ID-C Exam Dumps

 

Prepare for the US Green Building Council LEED AP Interior Design + Construction V4 exam with our extensive collection of questions and answers. These practice Q&A are updated according to the latest syllabus, providing you with the tools needed to review and test your knowledge.

QA4Exam focus on the latest syllabus and exam objectives, our practice Q&A are designed to help you identify key topics and solidify your understanding. By focusing on the core curriculum, These Questions & Answers helps you cover all the essential topics, ensuring you're well-prepared for every section of the exam. Each question comes with a detailed explanation, offering valuable insights and helping you to learn from your mistakes. Whether you're looking to assess your progress or dive deeper into complex topics, our updated Q&A will provide the support you need to confidently approach the US Green Building Council LEED-AP-ID-C exam and achieve success.

The questions for LEED-AP-ID-C were last updated on Apr 1, 2025.
  • Viewing page 1 out of 20 pages.
  • Viewing questions 1-5 out of 100 questions
Get All 100 Questions & Answers
Question No. 1

The Commissioning Authority (CxA) must report results, findings and recommendations directly to the

Show Answer Hide Answer
Correct Answer: A

The Commissioning Authority (CxA) plays a crucial role in ensuring that a building's systems are designed, installed, and calibrated to operate as intended. For the commissioning process to be effective and maintain its integrity, the CxA must have direct communication with the project's owner. Reporting results, findings, and recommendations directly to the owner ensures that the highest level of accountability is maintained, and it enables the owner to make informed decisions based on the commissioning outcomes. This direct line of communication is essential for addressing any issues that may arise and for implementing recommendations that may impact the project's performance, budget, or schedule. Reference:

LEED v4 for Interior Design and Construction Reference Guide, specifically the sections related to the roles and responsibilities of the Commissioning Authority (CxA) within the Energy and Atmosphere credits.


Question No. 2

Which of the following must be considered in order to meet Energy and Atmosphere Prerequisite, Fundamental Refrigerant Management if the tenant requires 24-hour cooling in a server room?

Show Answer Hide Answer
Correct Answer: B

Question No. 3

Which prerequisite and/or credits can be achieved by providing individual controls for lighting?

Show Answer Hide Answer
Correct Answer: C

Providing individual lighting controls helps to achieve the Energy and Atmosphere (EA) Credit for Optimize Energy Performance by allowing occupants to adjust lighting to suit task needs and preferences, which can reduce overall energy use. Additionally, it contributes to the Indoor Environmental Quality (EQ) Credit for Interior Lighting by offering personal control over the lighting in individual spaces, enhancing comfort and productivity.


Providing individual lighting controls in a space allows occupants to adjust lighting to meet their specific needs and preferences, contributing to energy savings and enhanced occupant comfort and well-being. This capability directly contributes to the Indoor Environmental Quality Credit, Interior Lighting, by promoting occupant control over lighting levels. Additionally, the ability to tailor lighting use to actual needs helps optimize the building's overall energy performance, contributing to the Energy and Atmosphere Credit, Optimize Energy Performance. By reducing unnecessary lighting use, individual controls contribute to the building's energy efficiency goals, aligning with the objectives of these two credits. Reference:

LEED v4 for Interior Design and Construction Reference Guide, particularly the sections on Indoor Environmental Quality Credit, Interior Lighting, and Energy and Atmosphere Credit, Optimize Energy Performance

Question No. 4

A project consists of both retail and office space. When deciding which LEED Interior Design and Construction rating system to use, the LEED AP should follow which of the following rules?

Show Answer Hide Answer
Correct Answer: B

When selecting a LEED Interior Design and Construction rating system, the LEED AP should use the rating system that is appropriate for the majority of the project's gross floor area. If more than 50% of the project's area can be appropriately rated under a particular system, then that system should be applied to the entire project.


LEED v4: Interior Design + Construction Guide1

LEED rating system selection guidance2.

When determining the most applicable LEED Interior Design and Construction rating system for a mixed-use project, such as one consisting of both retail and office space, the general guideline is to choose the rating system that is appropriate for the majority of the project's gross floor area. If a specific LEED rating system covers more than 50% of the project's gross floor area, it should be selected for the entire project. This approach ensures that the chosen rating system aligns closely with the predominant use of the project, facilitating a more relevant and effective sustainability strategy that addresses the primary functions and needs of the space. Reference:

LEED v4 for Interior Design and Construction Reference Guide, particularly the sections outlining how to choose the appropriate rating system for mixed-use projects

Question No. 5

A project needs 5,000 ft2 (464.5 m2) of raised flooring. The tenant wants to refurbish and install an existing raised floor from another building as part of the project. If this material will equate to 14% of the overall project materials cost, which credit would this contribute towards?

Show Answer Hide Answer
Correct Answer: C

Reusing existing materials from another building, like the raised flooring in this case, contributes to the LEED goal of reducing the demand for virgin materials and minimizing environmental impact. This reuse can be considered as part of the Building Life Cycle Impact Reduction credit, which falls under the umbrella of Materials and Resources credits. Specifically, Option 3 of this credit deals with building and material reuse. By refurbishing and reinstalling an existing raised floor, the tenant's actions demonstrate leadership in extraction practices because they are extending the lifecycle of existing materials, thereby reducing the need for new materials and the environmental burden associated with material extraction and processing.